The company

One of the regions with the highest growth rate in Canada

The problem

The region must build a road infrastructure investment plan annually respecting its commitments and its budgets. The selection of projects was a source of great debate and selected projects were not consistent with the highest priority projects in the eyes of elected officials.

The approach

After a thorough analysis of the decision making process using a rigorous mathematical approach, MELIORE detected bias in the processing and interpretation of the data. Following these steps, MELIORE was able to propose new and uncorrelated indicators for selection.

The benefits

The region was able to understand and explain why a project was more important than another. Consequently there was a better use of public funds.